Record the old meter's final reading and the new meter's start value in the same period.
ManagersUpdated
When a meter is swapped mid-month, both meters are billed for that period: the old one up to its final reading, the new one from its start value.
- Step 1: Open the period (it must be open or in review) and go to 1. Readings.
- Step 2: Find the old meter, open the row's ⋯ menu and choose Replace meter….
- Step 3: Enter the old meter's Final reading, the new meter's Serial number and Start value, and the date it was Replaced on.
- Step 4: Press Replace meter.
The old meter becomes inactive and shows "Replaced → (new serial)". The new meter appears in the list from now on.